Fencing is coming to River Park. Stoughton has hired a contractor to build a multi-use trail underpass beneath Fourth Street. Walkers and cyclists will be able to get between downtown and the riverfront without crossing traffic. The underpass is the visible part. The same contract also fills the old headrace and tailrace channels next to the 1906 Powerhouse. A city planning memo says that work has to be done before the building can be sold.

So a trail project is setting the pace for the riverfront's best-known building. The closures this winter are the first step in a sequence the city has been trying to start for more than a year.

What R.G. Huston was hired to build

Bids opened July 2, 2026. Strand Associates reviewed the three bids for the city, and they were far apart.

Contractor Base bid
R.G. Huston Company, Inc., Cottage Grove $4,914,300.00
Fischer Excavating, Inc. $5,032,051.00
Speedway Sand & Gravel, Inc. $7,462,081.50

The top two bids were about $118,000 apart. The third came in roughly $2.5 million above the low bid. On July 28, 2026, the Common Council voted 10–0 on resolution R-112-2026 to give the work to R.G. Huston.

Parks, Recreation & Forestry Superintendent Tony King's memo to the council lists the contract scope:

  • The Fourth Street trail underpass
  • River and shoreline improvements
  • Filling in the old headrace and tailrace channels
  • Cleanup of contaminated soil on the site
  • Trail lighting
  • Landscaping and related site work

The third item on that list ties the trail project to the Powerhouse.

Why the Powerhouse has been waiting on the trail

The Powerhouse is also known as Stoughton Power Plant No. 1. The Courier Hub has reported that city records date it to 1906 and described it as the old power plant on Fourth Street, at the time technically owned by the city's Redevelopment Authority.

On Nov. 13, 2025, Planning & Development Director Chris Munz-Pritchard sent an update to the Landmarks Commission that explains the holdup. "Prior to any sale of the building," the memo says, "the headrace and tailrace will need to be filled in." The channels fall under the Wisconsin DNR because the state has jurisdiction over navigable waterways. The memo says the work was slated for September 2025 and that DNR permits were still pending. It also notes that the tailrace sits in an area marked for remedial excavation and dredging. That timeline was being set alongside the infrastructure for the larger Riverfront Development.

Here is how the sequence has played out since:

  1. September 2025: Channel filling was originally scheduled, then held up while DNR permits were pending.
  2. Nov. 13, 2025: The planning memo describes the Powerhouse as "a very small part of an overall redeveloped area." That area covers the RDA Riverfront Site, Mandt Park, Riverfront Improvements Phase I and what the memo calls Water Park, Phase 2.
  3. July 2, 2026: Bids open for the underpass contract, which includes the channel work.
  4. July 8, 2026: The Redevelopment Authority lists "Powerhouse" only as a possible future agenda item and makes no decision.
  5. July 28, 2026: The council awards the contract 10–0.
  6. Oct. 20, 2026: The superintendent's report to the Parks Committee says the city is "still finalizing a few permits and answering DNR questions" and that the project "should be getting started soon."

The Courier Hub's report on the trail project draws the same connection from the city's news release. The work will make the Powerhouse property more accessible and "better position the building for future commercial and redevelopment opportunities." No buyer, use or sale has been approved, and filling the channels removes the requirement the city memo says must be met before any sale.

What changes on the trail, and for how long

The city's release, as reported by the Courier Hub, tells residents to expect construction in and around River Park "over the coming months." That includes temporary trail closures and changes to pedestrian access. The city does not expect a full closure of Fourth Street. Drivers may run into flaggers or temporary traffic control while equipment and trucks move in and out of the work site.

The city hasn't published a start date, specific detour routes or a completion date. The Parks Department's 2027–2031 capital plan lists $538,258 for "Trail, Underpass and Pedestrian Plaza" construction in 2027. That points to work continuing into next year. It is a budget line, though, and doesn't promise when the underpass will open. For anyone who walks or rides the river trail daily, the best place to watch is the Parks Committee's monthly superintendent report. The October report is where the "getting started soon" update appeared.

Who is paying for it

The July award memo lists $1,204,999 in outside grant money: a $979,999 Land and Water Conservation Fund grant and $225,000 in Municipal Flood Control grant funding. Previously approved city funding covers the rest. Measured against the $4,914,300 low bid, the grants cover about a quarter of the contract.

One city figure doesn't match. The October financial report in the Parks Committee packet lists $239,200 under "State Grants—River Restoration." The July memo listed $225,000 in flood control grant money. The two documents don't say whether the gap is a revised award or a difference in accounting categories.

The bigger riverfront plan this replaces

People who have followed the Yahara for a while may remember a much bigger idea. A city project analysis from May 2020 centered the riverfront on removing the Stoughton Dam and adding whitewater features, fish passage, canoe and kayak launches, trails, plazas and an underpass. That plan put dam removal, whitewater work, the underpass and a Water Street trail in a second phase. Mandt Park improvements and a Jefferson Street pedestrian bridge came in a third.

The contract awarded in 2026 is narrower. Its scope doesn't include a paddle launch or a whitewater feature. The current capital plan names the Yahara Riverpark Project but doesn't schedule dam removal or whitewater work. The 2020 plan is best read as an earlier idea. The underpass, the channel fill and the shoreline work are what is actually funded. Mayor Tim Swadley's comment in the city release, as the Courier Hub reported it, takes the long view: "The upgrades and projects at Mandt Park and the Riverfront will serve our community for generations."

Main Street while the river trail is fenced

With River Park partly closed, more of November happens a few blocks up East Main Street.

The Stoughton Chamber of Commerce and Visitor Center has moved to 144 E. Main St., with a grand opening on the calendar for Oct. 29. The Stoughton Opera House at 381 E. Main St. has a run of roots and string-band shows:

  • Thursday, Nov. 19: The Wood Brothers with Amelia Day
  • Friday, Nov. 20: The Travelin' McCourys
  • Friday, Dec. 4: Sarah Jarosz with special guest Jordan Tice

Two Saturdays belong to local makers. The Courier Hub reports that Innovation Center Stoughton is supporting the ninth annual Stoughton Children's Business Fair on Nov. 14, from 10 a.m. to 12:30 p.m. at River Bluff Middle School. Kids ages 6 to 14 run their own booths, and the fair is open to the public. On Nov. 28, the center hosts its first Makerspace Market from 9 a.m. to 3 p.m. at its building at 421 E. Main St. It's capped at 10 booths selling 3D-printed pieces, candles, soaps, jewelry, clothing, linocuts and laser-engraved goods. Executive director Ruth Phillips told the paper that people don't need a membership to take a class there.

If you own a home near River Park or downtown and want to know how the riverfront work could affect your home's value, our Stoughton neighborhood guide is a good place to start. When you're ready for numbers, The Collective Wisconsin can help. Request your free home valuation and we'll go through what the comparable sales near you show.

Partner in Success

Whether it’s your very first or the one you’ve always dreamed of. We will work hard for you, listen carefully to your needs, and stay committed to finding the right home for you.